[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907240,586,1,"单选题","（2020年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），现浇混凝土构件工程量计算正确的为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","坡道按设计图示尺寸以“m3”计算",false,{"key":16,"text":17,"correct":18},"B","架空式台阶按现浇楼梯计算",true,{"key":20,"text":21,"correct":14},"C","室外地坪按设计图示面积乘以厚度以“m3”计算",{"key":23,"text":24,"correct":14},"D","地沟按设计图示结构截面积乘以中心线长度以“m3”计算","P389-408 选项AC错误，散水、坡道、室外地坪，按设计图示尺寸以面积\"m2\"计算。 选项B正确，架空式混凝土台阶，按现浇楼梯计算。 选项D错误，电缆沟、地沟，按设计图示以中心线长度\"m\"计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]