[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907235,586,1,"单选题","（2020年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），石砌体工程量计算正确的为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","石台阶项目包括石梯带和石梯膀",false,{"key":16,"text":17,"correct":18},"B","石坡道按设计图示尺寸以水平投影面积计算",true,{"key":20,"text":21,"correct":14},"C","石护坡按设计图示尺寸以垂直投影面积计算",{"key":23,"text":24,"correct":14},"D","石挡土墙按设计图示尺寸以挡土面积计算","P385-389 选项A错误，石台阶项目包括石梯带（垂带），不包括石梯膀。 选项B正确，石坡道，按设计图示尺寸以水平投影面积\"m2\"计算。 选项C错误，石护坡，按设计图示尺寸以体积\"m3\"计算。 选项D错误，石挡土墙，按设计图示尺寸以体积\"m3\"计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]