[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907233,586,1,"单选题","（2020年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），墙面抹灰工程量计算正确的为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","墙面抹灰中墙面勾缝不单独列项",false,{"key":16,"text":17,"correct":14},"B","有吊顶天棚的内墙面抹灰抹至吊顶以上部分应另行计算",{"key":19,"text":20,"correct":21},"C","墙面水刷石按墙面装饰抹灰编码列项",true,{"key":23,"text":24,"correct":14},"D","墙面抹石膏灰浆按墙面装饰抹灰编码列项","P426-429 选项A错误，墙面一般抹灰、墙面装饰抹灰、墙面勾缝、立面砂浆找平层，按设计图示尺寸以面积\"m2\"计算。 选项B错误，有吊顶天棚的内墙面抹灰，抹至吊顶以上部分在综合单价中考虑，不另计算。 选项C正确，选项D错误，墙面抹石灰砂浆，水泥砂浆、混合砂浆、聚合物水泥砂浆、麻刀石灰浆、石膏灰浆等按墙面一般抹灰列项；墙面水刷石、斩假石、干粘石、假面砖等按墙面装饰抹灰列项。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]