[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907232,586,1,"单选题","（2020年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），幕墙工程工程计算正确的为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应扣除与带骨架幕墙同种材质的窗所占面积",false,{"key":16,"text":17,"correct":14},"B","带肋全玻幕墙玻璃肋工程量应单独计算",{"key":19,"text":20,"correct":14},"C","带骨架幕墙按图示框内围尺寸以面积计算",{"key":22,"text":23,"correct":24},"D","带肋全玻幕墙按展开面积计算",true,"P426-429 选项AC错误，带骨架幕墙，按设计图示框外围尺寸以面积\"m2\"计算。与幕墙同种材质的窗所占面积不扣除。 选项B错误，选项D正确，带肋全玻幕墙按展开面积计算。带肋全玻璃幕墙是指玻璃幕墙带玻璃肋，玻璃肋的工程量并入到玻璃幕墙工程量内计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]