[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},907229,586,1,"单选题","（2020年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），打桩项目工作内容应包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","送桩",true,{"key":16,"text":17,"correct":18},"B","承载力检测",false,{"key":20,"text":21,"correct":18},"C","桩身完整性检测",{"key":23,"text":24,"correct":18},"D","截（凿）桩头","P382-385 打桩的工程内容中包括了接桩和送桩，不需要单独列项，应在综合单价中考虑。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]