[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907228,586,1,"单选题","（2020年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），屋面防水工程量计算正确的为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","斜屋面按水平投影面积计算",false,{"key":16,"text":17,"correct":14},"B","女儿墙处弯起部分应单独列项计算",{"key":19,"text":20,"correct":21},"C","防水卷材搭接用量不另行计算",true,{"key":23,"text":24,"correct":14},"D","屋面伸缩缝弯起部分单独列项计算","P418-422 选项A错误，斜屋顶（不包括平屋顶找坡）按斜面积计算； 选项BD错误，屋面的女儿墙、伸缩缝和天窗等处的弯起部分，并入屋面工程量内； 选项C正确，屋面防水搭接及附加层用量不另行计算，在综合单价中考虑。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]