[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907225,586,1,"单选题","（2019年真题）某较为平整的软岩施工场地,设计长度为30m,宽为10m,开挖深度为0.8m。根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013）,开挖石方清单工程量为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","沟槽石方工程量300m2",false,{"key":16,"text":17,"correct":14},"B","基坑石方工程量240m3",{"key":19,"text":20,"correct":14},"C","管沟石方工程量30m",{"key":22,"text":23,"correct":24},"D","一般石方工程量240m3",true,"沟槽、基坑、一般土方的划分为：底宽≤7m且底长＞3倍底宽为沟槽；底长≤3倍底宽且底面积≤150m2为基坑；超出上述范围则为一般土方。底宽10m＞7m，长度30m=3倍底宽且底面积＞150m2为基坑，所以为一般土方，工程量为30×10×0.8=240m3",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]