[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907224":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907224,586,1,"单选题","（2019年真题）某建筑物砂土场地,设计开挖面积为20m×7m,自然地面标高为-0.2m,设计室外地坪标高为-0.3m,设计开挖底面标高为-1.2m。根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013）,土方工程清单工程量计算应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","执行挖一般土方项目,工程量为140m3",false,{"key":16,"text":17,"correct":14},"B","执行挖一般土方项目,工程量为126m3",{"key":19,"text":20,"correct":21},"C","执行挖基坑土方项目,工程量为140m3",true,{"key":23,"text":24,"correct":14},"D","执行挖基坑土方项目,工程量为126m3","20*7*（1.2-0.2）=140m3",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]