[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907221":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907221,586,1,"单选题","（2019年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013）,现浇混凝土肢剪力墙工程量计算正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","短肢剪力墙按现浇混凝土异形墙列项",false,{"key":16,"text":17,"correct":14},"B","各肢截面高度与厚度之比大于5时按现浇混凝土矩形柱列项",{"key":19,"text":20,"correct":14},"C","各肢截面高度与厚度之比小于4时按现浇混凝土墙列项",{"key":22,"text":23,"correct":24},"D","各肢截面高度与厚度之比为4.5时,按短肢剪力墙列项",true,"短肢剪力墙是指截面厚度不大于300mm、各肢截面高度与厚度之比的最大值大于4但不大于8的剪力墙（4\u003C各肢截面高度与厚度之比≤8）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]