[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907213,586,1,"单选题","（2019年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013）,打预制钢筋混凝土方桩清单工程量计算正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","打桩按打入实体长度（不包括桩尖）计算,以\"m\"计量",false,{"key":16,"text":17,"correct":18},"B","截桩头按设计桩截面乘以桩头长度以体积计算,以\"m3\"计量",true,{"key":20,"text":21,"correct":14},"C","接桩按接头数量计算,以\"个\"计量",{"key":23,"text":24,"correct":14},"D","送桩按送入长度计算,以\"m\"计量","接桩和送桩不单独列项计算工程量。打预制钢筋混凝土方庄可以按长度计算，但应包括桩尖的长度。截桩头可以按体积计算也可以按数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]