[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907208,586,1,"单选题","（2014年真题）某建筑工程挖土方工程量需要通过现场签证核定，已知用斗容量为1.5m3的轮胎式装载机运土500车，则挖土工程量应为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","501.92m3",false,{"key":16,"text":17,"correct":18},"B","576.92m3",true,{"key":20,"text":21,"correct":14},"C","623.15m3",{"key":23,"text":24,"correct":14},"D","750m3","土石方体积应按挖掘前的天然密实体积计算，如需按天然密实体积折算时，挖土工程量=1.5×500\u002F1.3=576.92m3",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]