[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},907203,586,1,"单选题","（2018年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），钢木屋架工程应（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按设计图示数量以榀计算",true,{"key":16,"text":17,"correct":18},"B","按设计图示尺寸以体积计算",false,{"key":20,"text":21,"correct":18},"C","按设计图示尺寸以下弦中心线的长度计算",{"key":23,"text":24,"correct":18},"D","按设计图示尺寸以上部屋面斜面面积计算","考查木结构工程工程量计算。钢木屋架以榀计量，按设计图示数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]