[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},907201,586,1,"单选题","（2018年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），钢屋架工程量计算应（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不扣除孔眼的质量",true,{"key":16,"text":17,"correct":18},"B","按设计用量计算螺栓质量",false,{"key":20,"text":21,"correct":18},"C","按设计用量计算铆钉质量",{"key":23,"text":24,"correct":18},"D","按设计用量计算焊条质量","以榀计量时，按设计图示数量计算；以吨计量时，按设计图示尺寸以质量计算，不扣除孔眼的质量，焊条、铆钉、螺栓等不另增加质量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]