[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907186,586,1,"单选题","（2013年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），某建筑物首层建筑面积为2000㎡，场地内有部分150mm以内的挖土用6.5T自卸汽车（斗容量4.5m3）运土，弃土共计20车，运距150m，则平整场地的工程量应为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","69.2m3",false,{"key":16,"text":17,"correct":14},"B","83.3m3",{"key":19,"text":20,"correct":14},"C","90m3",{"key":22,"text":23,"correct":24},"D","2000㎡",true,"平整场地按设计图示尺寸以建筑物首层建筑面积计算，单位：㎡，在平整场地若需要外运土方或取土回填时，在清单项目特征中应描述弃土运距或取土运距，其报价应包括在平整场地项目中;当清单中没有描述弃、取土运距时，应注明由投标人根据施工现场实际情况自行考虑到投标报价中。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]