[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907176,586,1,"单选题","（2014年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50584-2013）规定，关于厂库房大门工程量计算，说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","防护铁丝门按设计数量以质量计算",false,{"key":16,"text":17,"correct":14},"B","金属格栅门按设计图示门框以面积计算",{"key":19,"text":20,"correct":14},"C","钢制花式大门按设计图示数量以质量计算",{"key":22,"text":23,"correct":24},"D","全钢板大门按设计图示洞口尺寸以面积计算",true,"A.防护铁丝门按设计图示数量计算，或按设计图示门框或扇以面积计算；B.金属格栅门按设计图示数量计算，或按设计图示洞口尺寸以面积计算；C.钢制花式大门按设计图示数量计算，或按设计图示门框或扇以面积计算；D全钢板大门按设计图示数量计算或按设计图示洞口尺寸以面积计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]