[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},907173,586,1,"单选题","（2014年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50584-2013）规定，关于预制混凝土构件工程量计算，说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预制组合屋架，按设计图示尺寸以体积计算，不扣除预埋铁件所占体积",true,{"key":16,"text":17,"correct":18},"B","预制网架板，按设计图示尺寸以体积计算，不扣除孔洞占体积",false,{"key":20,"text":21,"correct":18},"C","预制空心板，按设计图示尺寸以体积计算，不扣除空心板空洞所占体积",{"key":23,"text":24,"correct":18},"D","预制混凝土楼梯，按设计图示尺寸以体积计算，不扣除空心踏步板空洞体积","预制混凝土屋架按设计图示尺寸以体积计算，单位m3。B.预制网架板，扣除孔洞占体积；C.预制空心板扣除空心板空洞所占体积；D.预制混凝土楼梯，扣除空心踏步板空洞体积。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]