[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907170,586,1,"单选题","（2014年真题）某建筑首层建筑面积500㎡，场地较为平整，其自然地面标高为+87.5m，设计室外地面标高为+87.15m，则其场地土方清单列项和工程量分别是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按平整场地列项：500㎡",false,{"key":16,"text":17,"correct":14},"B","按一般土方列项：500㎡",{"key":19,"text":20,"correct":14},"C","按平整场地列项：175m3",{"key":22,"text":23,"correct":24},"D","按一般土方列项：175m3",true,"因为厚度=87.5-87.15=0.35米＞0.3米，所以应按一般土方列项。工程量应该=500×0.35=175m3",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]