[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907139,586,1,"单选题","（2017年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），混凝土框架柱工程量应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按设计图示尺寸扣除板厚所占部分以体积计算",false,{"key":16,"text":17,"correct":14},"B","区别不同截面以长度计算",{"key":19,"text":20,"correct":21},"C","按设计图示尺寸不扣除梁所占部分以体积计算",true,{"key":23,"text":24,"correct":14},"D","按柱基上表面至梁底面部分以体积计算","框架柱的柱高应自柱基上表面至柱顶高度计算（断梁不断柱）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]