[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907138,586,1,"单选题","（2017年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），砌筑工程垫层工程量应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按基坑（槽）底设计图示尺寸以面积计算",false,{"key":16,"text":17,"correct":14},"B","按垫层设计宽度乘以中心线长度以面积计算",{"key":19,"text":20,"correct":21},"C","按设计图示尺寸以体积计算",true,{"key":23,"text":24,"correct":14},"D","按实际铺设垫层面积计算","除混凝土垫层外，没有包括垫层要求的清单项目应按该垫层项目编码列项，例如:灰土垫层、楼地面等（非混凝土）垫层。其工程量按设计图示尺寸以体积计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]