[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},907134,586,1,"单选题","（2017年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB\u002FT50854-2013）,地基处理工程量计算正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","换填垫层按设计图示尺寸以体积计算",true,{"key":16,"text":17,"correct":18},"B","强夯地基按设计图示处理范围乘以处理深度以体积计算",false,{"key":20,"text":21,"correct":18},"C","填料振冲桩以填料体积计算",{"key":23,"text":24,"correct":18},"D","水泥粉煤灰碎石桩按设计图示尺寸以体积计算","换填垫层工程量按设计图示尺寸以体积计算。预压地基、强旁地基、振冲密实（不填料），工程量均按设计图示处理范围以面积计算。砂石桩以米计量，按设计图示尺寸以桩长（包括桩尖）计算;以立方米计量，按设计桩截面乘以桩长（包括桩尖）以体积计算。水泥粉煤灰碎石桩、穷实水泥土桩、石灰桩、灰土（土）挤密桩的工程量均以米计量，按设计图示尺寸以桩长（包括桩尖）计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]