[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},907114,586,1,"单选题","（2015年真题）对地下工程喷射混凝土施工说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","喷嘴处水压应比工作风压大",true,{"key":16,"text":17,"correct":18},"B","工作风压随送风距离增加而调低",false,{"key":20,"text":21,"correct":18},"C","骨料回弹率与一次喷射厚度成正此",{"key":23,"text":24,"correct":18},"D","喷嘴与作业面之间的距离越小，回弹率越低","本题考查的是隧道工程施工技术。选项B错误，当输送距离变化时，工作风压可参考以下数值：水平输送距离每增加100m，工作风压应提高0.08-0.1MPa;倾斜向下喷射，每增加100m，工作风压应提高0.05-0.07MPa;垂直向上喷射每增加10m，工作风压应提高0.02-0.03MPa,选项C错误，一次喷射厚度太薄，喷射时骨料易产生大的回弹；一次喷射的太厚：易出现喷层下坠、流淌，或与基层面间出现空壳；选项D错误，经验表明，喷头与喷射作业面的最佳距离为1m，当喷头与喷射作业面间的距离≤0.75m或≥1.25m,喷射的回弹率可达25%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]