[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907073":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907073,586,1,"单选题","（2020年真题）钢筋混凝土预制桩在砂夹卵石层和坚硬土层中沉桩，主要沉桩方式（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","静力压桩",false,{"key":16,"text":17,"correct":14},"B","锤击沉桩",{"key":19,"text":20,"correct":14},"C","振动沉桩",{"key":22,"text":23,"correct":24},"D","射水沉桩",true,"P183-200 射水沉桩法的选择应视土质情况而异，在砂夹卵石层或坚硬土层中，一般以射水为主，锤击或振动为辅；在亚黏土或黏土中，为避免降低承载力，一般以锤击或振动为主，以射水为辅，并应适当控制射水时间和水量，下沉空心桩，一般用单管内射水。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]