[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907061":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907061,586,1,"单选题","（2017年真题）先张法预应力混凝土构件施工，其工艺流程为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","支底模—支侧模—张拉钢筋—养护、拆模—放张钢筋",false,{"key":16,"text":17,"correct":14},"B","支底模—张拉钢筋—支侧模—浇筑混凝土—护、拆模",{"key":19,"text":20,"correct":21},"C","支底模—预应力钢筋安放—张拉钢筋—支侧模—浇混凝土—拆模—放张钢筋",true,{"key":23,"text":24,"correct":14},"D","支底模—钢筋安放—支侧模—张拉钢筋—交筑混凝土—放张钢筋—拆模","先张法的工艺流程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]