[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907055":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":21},907055,586,1,"单选题","（2018年真题）在剪力墙体系和筒体体系高层建筑的混凝土结构施工时，高效、安全一次性模板投资少的模板形式应为（）。 A.组合模板B滑升模板 C.爬升模板 D.台模",[11,14,16,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D","爬升模板简称爬模，国外亦称跳模，是施工剪力墙体系和筒体体系的钢筋混凝土结构高层建筑的一种有效的模板体系。",{"id":6,"name":23,"category":24,"favorite":25},"建设工程技术与计量（土建）","建筑工程",0]