[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907043":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},907043,586,1,"单选题","（2014年真题）关于钢筋混凝土预制桩加工制作，说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","长度在10cm以上的桩必须工厂预制",false,{"key":16,"text":17,"correct":14},"B","重叠法预制不宜超过5层",{"key":19,"text":20,"correct":14},"C","重叠法预制下层桩强度达到设计强度70%以上时方可灌注上层桩",{"key":22,"text":23,"correct":24},"D","桩的强度达到设计强度的70%方可起吊",true,"钢筋混凝土预制桩应在混凝土强度达到设计强度的70%方可起吊。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]