[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907036,586,1,"单选题","（2014年真题）采用明排水法开挖基坑，在基坑开挖过程中设置的集水坑应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","布置在基础范围以内",false,{"key":16,"text":17,"correct":14},"B","布置在基坑底部中央",{"key":19,"text":20,"correct":21},"C","布置在地下水走向的上游",true,{"key":23,"text":24,"correct":14},"D","经常低于挖土面1.0m以上","采用明排水开挖基坑时，集水坑应设置在基础范围以外，地下水走向的上游。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]