[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},907033,586,1,"单选题","（2015年真题）静力压桩正确的施工工艺流程是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定位—吊桩—对中—压桩—接桩—压桩—送桩—切割桩头",true,{"key":16,"text":17,"correct":18},"B","吊桩—定位—对中—压桩—送桩—压桩—接桩—切割桩头",false,{"key":20,"text":21,"correct":18},"C","对中—吊桩—插桩—送桩—静压—接桩—压桩—切割桩头",{"key":23,"text":24,"correct":18},"D","吊桩—定位—压桩—送桩—接桩—压桩—切割桩头","本题考查的是地基与基础工程施工。静力压桩由于受设备行程的限制，在一般情况下是分段预制、分段压入、逐段压入、逐段接长，其施工工艺程序为：测量定位——压桩机就位——吊桩、插桩——桩身对中调直——静压沉桩——接桩——再静压沉桩——送桩——终止压桩——切割桩头。当第一节桩压入土中，其上端距地面2m左右时，将第二节桩接上、继续压入。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]