[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907032":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907032,586,1,"单选题","（2015年真题）打桩机正确的打桩顺序为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先外后内",false,{"key":16,"text":17,"correct":18},"B","先大后小",true,{"key":20,"text":21,"correct":14},"C","先短后长",{"key":23,"text":24,"correct":14},"D","先浅后深","本题考查的是地基与基础工程施工。打桩应避免自外向内，或从周边向中间进行。当桩基的设计标高不同时，打桩顺序应先深后浅；当桩的规格不同时，打桩顺序宜先大后小，先长后短。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]