[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906943,586,1,"单选题","（2017年真题）地铁车站的通过能力应按该站远期超高峰设计客流量确定。超高峰设计客流量为该站预测远期高峰小时客流量的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.1～1.4倍",true,{"key":16,"text":17,"correct":18},"B","1.1～1.5倍",false,{"key":20,"text":21,"correct":18},"C","1.2～1.4倍",{"key":23,"text":24,"correct":18},"D","1.2～1.5倍","超高峰设计客流量为该站预测远期高峰小时客流量（或客流控制时期的高峰小时客流量）的1.1-1.4倍。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]