[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906821":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906821,586,1,"单选题","对于国家投资的项目，施工图的建筑面积不得超过初步设计的（ ），否则必须重新报批。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2%",false,{"key":16,"text":17,"correct":14},"B","3%",{"key":19,"text":20,"correct":14},"C","4%",{"key":22,"text":23,"correct":24},"D","5%",true,"2020版教材P349 根据项目立项批准文件所核准的建筑面积，是初步设计的重要控制指标。对于国家投资的项目，施工图的建筑面积不得超过初步设计的5%，否则必须重新报批。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]