[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906785,586,1,"单选题","某建筑物一层平面图和屋顶平面图如图所示，屋面采用卷材防水，女儿墙部分的弯起高度为250mm，根据《房屋建筑与装饰工程工程量计算规范》GB?50854—2013，屋面卷材防水工程量应为（ ）m2。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","261．69",false,{"key":16,"text":17,"correct":14},"B","270．75",{"key":19,"text":20,"correct":21},"C","271．26",true,{"key":23,"text":24,"correct":14},"D","280．45","屋面卷材防水、屋面涂膜防水，按设计图示尺寸以面积“m2”计算。斜屋顶（不包括平屋顶找坡）按斜面积计算，平屋顶按水平投影面积计算。不扣除房上烟囱、风帽底座、风道、屋面小气窗和斜沟所占面积。屋面的女儿墙、伸缩缝和天窗等处的弯起部分，并入屋面工程量内。正确的计算方法是：屋面卷材防水工程量为： S=（28+0．5-0．24×2）×（9+0．5-0．24×2）+[（28+0．5-0．24×2）+（9+0．5-0．24×2）]×2×0．25=271．26（m2）2020版教材418-422",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]