[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906781":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906781,586,1,"单选题","一现浇钢筋混凝土柱下杯基础（如图），柱断面400mm×700mm，则该基础的混凝土工程量为（ ）m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4．242",true,{"key":16,"text":17,"correct":18},"B","3．542",false,{"key":20,"text":21,"correct":18},"C","4．278",{"key":23,"text":24,"correct":18},"D","4．351","现浇混凝土基础应以体积立方米计。计算该基础体积可看成由最下的六面体，加中间的实心四棱台，加最上的实心六面体，再减去杯口槽体积。最下六面体：3.2×2.0×0.4=2.56（m3） 2020版教材389-408",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]