[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906772,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB?50854，土石方工程中工程量可以长度计算的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","冻土开挖",false,{"key":16,"text":17,"correct":14},"B","挖淤泥、流砂",{"key":19,"text":20,"correct":14},"C","土石方回填",{"key":22,"text":23,"correct":24},"D","管沟石方",true,"根据《房屋建筑与装饰工程工程量计算规范》GB?50854，冻土开挖，按设计图示尺寸开挖面积乘以厚度以体积“m3”计算。 挖淤泥、流沙，按设计图示位置、界限以体积“m3”计算。回填方，按设计图示尺寸以体积“m3”计算。 管沟石方以“m”计量，按设计图示以管道中心线长度计算；以“m3”计量，按设计图示截面积乘以长度以体体积“m3”计算。2020版教材P372-378",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]