[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906771,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB?50854—2013，某墙基础采用有梁式带形混凝土垫层，垫层宽1300mm，墙中心线为50m，墙厚240mm，挖土深度为1．6m，则该基础土方工程量为（ ）m3。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","98",false,{"key":16,"text":17,"correct":14},"B","100",{"key":19,"text":20,"correct":21},"C","104",true,{"key":23,"text":24,"correct":14},"D","108","根据《房屋建筑与装饰工程工程量计算规范》GB 50854—2013，挖沟槽土方及挖基坑土方的计算规则是按设计图示尺寸以基础垫层底面积乘以挖土深度计算。单位：m3。此题1.3*50*1.6=104m3。2020版教材P372-378",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]