[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},906726,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013，关于基坑与边坡支护工程量计算的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地下连续墙按设计图示尺寸以长度计算",false,{"key":16,"text":17,"correct":18},"B","咬合灌注桩按设计图示尺寸以桩长计算",true,{"key":20,"text":21,"correct":14},"C","喷射混凝土按设计图示以长度计算",{"key":23,"text":24,"correct":14},"D","型钢桩按照设计图示尺寸以桩长计算","2020版教材P379 本题考查的是地基处理与边坡支护工程。选项A错误，地下连续墙按设计图示墙中心线长乘以厚度乘以槽深以体积\"m3\"计算。 选项B正确，咬合灌注桩以\"m\"计量，按设计图示尺寸以桩长计算；以\"根\"计量，按设计图示数量计算。 选项C错误，喷射混凝土（水泥砂浆），按设计图示尺寸以面积\"m2\"计算。 选项D错误，型钢桩以\"t\"计量，按设计图示尺寸以质量计算，以\"根\"计量，按设计图示数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]