[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906717,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013，下列有关分项工程工程量计算，不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","瓦屋面按设计图示尺寸以斜面积计算",false,{"key":16,"text":17,"correct":14},"B","膜结构屋面按设计图示尺寸以需要覆盖的水平投影面积计算",{"key":19,"text":20,"correct":14},"C","屋面排水管按设计室外散水上表面至檐口的垂直距离以长度计算",{"key":22,"text":23,"correct":24},"D","屋面变形缝防水按设计尺寸以面积计算",true,"2020版教材P420 本题考查的是屋面及防水工程。屋面变形缝，按设计图示以长度“m”计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]