[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906709,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013规定，有关木结构工程量计算，说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","木柱区分不同规格以高度计算",false,{"key":16,"text":17,"correct":14},"B","木屋架按照图示面积计算",{"key":19,"text":20,"correct":14},"C","钢木屋架、钢拉杆、连接螺栓需要单独列项计算",{"key":22,"text":23,"correct":24},"D","木屋架的马尾、折角应按相关屋架项目编码列项",true,"2020版教材P413 本题考查的是木结构。选项A错误，木柱、木梁，按设计图示尺寸以体积“m3”计算。 选项B错误，木屋架以\"榀\"计量时，按设计图示数量计算：以\"m3\"计量时，按设计图示的规格尺寸以体积计算。 选项C错误，屋架中钢拉杆、钢夹板等应包括在清单项目的综合单价内。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]