[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},906702,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB 50854--2013，现浇混凝土墙工程量应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","扣除突出墙面部分体积",false,{"key":16,"text":17,"correct":18},"B","扣除面积为0.33m2孔洞体积",true,{"key":20,"text":21,"correct":14},"C","将伸入墙内的梁头计入",{"key":23,"text":24,"correct":14},"D","扣除预埋铁件体积","2020版教材P392 根据《房屋建筑与装饰工程工程量计算规范》GB 50854-2013，墙垛及突出墙面部分并入墙体体积内计算。不扣除构件内钢筋、预埋铁件所占体积。扣除门窗洞口及单个面积0.3㎡的孔洞所占体积。现浇混凝土梁按设计图示尺寸以体积计算。不扣除构件内钢筋、预埋铁件所占体积，伸入墙内的梁头、梁垫并入梁体积内。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]