[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},906684,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854-2013规定，关于现浇混凝土柱的工程量计算正确的为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有梁板的柱按设计图示截面积乘以柱基以上表面或楼板上表面至上一层楼板底面之间的高度以体积计算",false,{"key":16,"text":17,"correct":18},"B","无梁板的柱按设计图示截面积乘以柱基以上表面或楼板上表面至柱帽下表面之间的高度以体积计算",true,{"key":20,"text":21,"correct":14},"C","框架柱按柱基上表面至柱顶高度以米计算",{"key":23,"text":24,"correct":14},"D","构造柱按设计柱高以米计算","2020版教材P391 现浇混凝土包括矩形柱、构造柱、异形柱按设计图示尺寸以体积计算。 有梁板的柱高，应自柱基上表面（或楼板上表面）至上一层楼板上表面之间的高度计算。 无梁板的柱高，应自柱基上表面（或楼板上表面）至柱帽下表面之间的高度计算。框架柱的柱高应自柱基上表面至柱顶高度计算。 构造柱按全高计算",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]