[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906674,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854-2013，关于预制混凝土构件工程量计算，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如以构件数量作为计量单位，特征描述中必须说明单件体积",true,{"key":16,"text":17,"correct":18},"B","异形柱应扣除构件内预埋铁件所占体积，铁件另计",false,{"key":20,"text":21,"correct":18},"C","大型板应扣除单个尺寸≤300mm×300mm的孔洞所占体积",{"key":23,"text":24,"correct":18},"D","空心板不扣除空洞体积","2020版教材P395 选项B，不扣除构件内钢筋、预埋铁件所占体积；选项C，大型板不扣除单个尺寸≤300mm×300mm的孔洞所占体积；选项D，空心板扣除空洞体积。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]