[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},906648,586,1,"单选题","根据《建设工程工程量清单计价规范》GB50500—2013，下列关于柱帽的工程量计算叙述错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现浇混凝土无梁板按板和柱帽体积之和计算",false,{"key":16,"text":17,"correct":18},"B","现浇混凝土无梁板的柱高，应自柱基上表面至柱帽上表面之间的高度计算",true,{"key":20,"text":21,"correct":14},"C","柱饰面按设计图示饰面外围尺寸以面积计算，柱帽并入相应柱饰面工程量内",{"key":23,"text":24,"correct":14},"D","保温隔热天棚按设计图示尺寸以面积计算，柱帽保温隔热并入天棚保温隔热工程量","2020版教材P391 本题考查的是混凝土及钢筋混凝土工程。选项B错误，无梁板的柱高，应自柱基上表面（或楼板上表面）至柱帽下表面之间的高度计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]