[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906646,586,1,"单选题","下列措施项目中，费用的计算不使用日历天数的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","满堂脚手架",true,{"key":16,"text":17,"correct":18},"B","施工排水",false,{"key":20,"text":21,"correct":18},"C","垂直运输",{"key":23,"text":24,"correct":18},"D","施工降水","2020版教材P440 本题考查的是措施项目。满堂脚手架按搭设的水平投影面积计算。 施工排水、降水，按排、降水日历天数\"昼夜\"计算。 垂直运输，按建筑面积“m2”计算，或按施工工期日历天数\"天\"计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]