[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906645,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013规定，关于现浇混凝土柱工程量计算，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","框架柱的柱高应自柱基上表面至柱顶高度计算",true,{"key":16,"text":17,"correct":18},"B","构造柱嵌接墙体部分（马牙槎）不计算工程量",false,{"key":20,"text":21,"correct":18},"C","有梁板矩形独立柱工程量按柱设计截面积乘以自柱基底面至板面高度以体积计算",{"key":23,"text":24,"correct":18},"D","无梁板矩形柱工程量按柱设计截面积乘以自楼板上表面至柱帽上表面高度以体积计算","2020版教材P390~391 本题考查的是混凝土及钢筋混凝土工程。选项B错误，构造柱嵌接墙体部分并入柱身体积计算。 选项C错误，有梁板矩形柱工程量按柱设计截面积乘以柱高以体积计算。柱高应自柱基上表面（或楼板上表面）至上一层楼板上表面之间的高度计算。 选项D错误，无梁板矩形柱工程量按柱设计截面积乘以柱高以体积计算。柱高应自柱基上表面（或楼板上表面）至柱帽下表面之间的高度计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]