[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906643,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013规定，关于天棚装饰工程量计算，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","回风口按设计图示数量计算",true,{"key":16,"text":17,"correct":18},"B","灯带（槽）按设计图示尺寸以延长米计算",false,{"key":20,"text":21,"correct":18},"C","送风口按设计图示尺寸以结构内边线面积计算",{"key":23,"text":24,"correct":18},"D","灯带（槽）按设计图示尺寸以框中心线面积计算","2020版教材P430 本题考查的是天棚工程。选项A正确，C错误，送风口、回风口，按设计图示数量\"个\"计算。选项B、C错误，灯带（槽），按设计图示尺寸以框外围面积“m2”计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]