[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906611,586,1,"单选题","在建设工程工程量清单中，分部分项工程量的计算规则大多是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按不同施工方法和实际用量计算",false,{"key":16,"text":17,"correct":14},"B","按不同施工数量和加工余量之和计算",{"key":19,"text":20,"correct":14},"C","按工程实体总量净量和加工余量之和计算",{"key":22,"text":23,"correct":24},"D","按工程实体尺寸的净量计算",true,"本题考查的是工程量计算规范。采用工程量计算规则计算的工程量一般为施工图纸的净量，不考虑施工余量。 2020版教材P326-327",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]