[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906609,586,1,"单选题","《房屋建筑与装饰工程工程量计算规范》GB50854—2013，工程量清单项目的补充涵盖内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目编码和项目名称",false,{"key":16,"text":17,"correct":14},"B","项目特征和计量单位",{"key":19,"text":20,"correct":21},"C","主要施工方法和技术",true,{"key":23,"text":24,"correct":14},"D","包含的工作内容","本题考查的是工程量计算规范。工程量清单项目的补充应包括项目编码、项目名称、项目特征、计量单位、工程量计算规则以及包含的工作内容，按工程量计算规范附录中相同的列表方式表述。不能计量的措施项目，需附有补充项目的名称、工作内容及包含范围。 2020版教材P327-332",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]