[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906599,586,1,"单选题","隧道工程喷射混凝土施工，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作风压应随输送管距增加而降低",false,{"key":16,"text":17,"correct":14},"B","喷嘴与作业面的距离应小于0.5m",{"key":19,"text":20,"correct":21},"C","喷嘴水压通常应比工作风压大",true,{"key":23,"text":24,"correct":14},"D","喷射混凝土骨料含水率应大于8%","2020版教材P314 本题考查的是隧道工程施工技术。 水压一般比工作风压大0.10MPa左右为宜。 A：应该是：工作风压应随输送管距增加而增加。 B：应该是：喷头与喷射作业面的最佳距离为1m。 D：应该是：喷射混凝土所用骨料的含水率，一般以5%-7%为宜。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]