[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906597":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906597,586,1,"单选题","单元槽段宜采用间隔一个或多个槽段的跳幅施工顺序，每一个单元槽段，挖槽分段不宜超过（ ）个。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","2020版教材P297 本题考查的是地下连续墙施工技术。划分单元槽段时还应考虑接头的位置，接头应避免设在转角处及地下连续墙与内部结构的连接处，以保证地下连续墙有较好的整体性；单元槽段的划分还与接头形式有关。单元槽段宜采用间隔一个或多个槽段的跳幅施工顺序。每个单元槽段，挖槽分段不宜超过3个。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]