[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906589":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906589,586,1,"单选题","地下连续墙施工工艺流程（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","挖导沟→筑导墙→挖槽→吊放接头管（接头箱）→吸泥、清底、刷壁→吊放钢筋笼→浇筑混凝土→插入混凝土导管→结束",false,{"key":16,"text":17,"correct":14},"B","挖导沟→吸泥、清底、刷壁→筑导墙→挖槽→吊放钢筋笼→吊放接头管（接头箱）→插入混凝土导管→浇筑混凝土→结束",{"key":19,"text":20,"correct":21},"C","挖导沟→筑导墙→挖槽→吸泥、清底、刷壁→吊放接头管（接头箱）→吊放钢筋笼→插入混凝土导管→浇筑混凝土一结束",true,{"key":23,"text":24,"correct":14},"D","筑导墙→挖导沟→挖槽→吸泥、清底、刷壁→浇筑混凝土→吊放接头管（接头箱）→吊放钢筋笼→插入混凝土导管一结束","地下连续墙施工工艺流程为：挖导沟→筑导墙→挖槽→吸泥、清底、刷壁→吊放接头管（接头箱）→吊放钢筋笼→插入混凝土导管→浇筑混凝土→结束。 2020版教材P294-302",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]