[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906588":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906588,586,1,"单选题","型钢水泥复合搅拌桩支护技术施工工艺流程（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","消除地下障碍物、平整场地→开挖导沟→置放导轨与定位卡→SMW搅拌桩机就位→钻进与搅拌→插入型钢并固定→撇除导轨→施工顶圈梁→支护施工完毕",true,{"key":16,"text":17,"correct":18},"B","消除地下障碍物、平整场地→开挖导沟→SMW搅拌桩机就位→置放导轨与定位卡→钻进与搅拌→撇除导轨→插入型钢并固定→施工顶圈梁→支护施工完毕",false,{"key":20,"text":21,"correct":18},"C","消除地下障碍物、平整场地→置放导轨与定位卡→开挖导沟→SMW搅拌桩机就位→钻进与搅拌→插入型钢并固定→施工顶圈梁→撇除导轨→支护施工完毕",{"key":23,"text":24,"correct":18},"D","消除地下障碍物、平整场地→开挖导沟→施工顶圈梁→SMW搅拌桩机就位→钻进与搅拌→置放导轨与定位卡→插入型钢并固定→撇除导轨→支护施工完毕","型钢水泥复合搅拌桩支护技术施工工艺流程为：消除地下障碍物、平整场地→开挖导沟→置放导轨与定位卡→SMW搅拌桩机就位→钻进与搅拌→插入型钢并固定→撇除导轨→施工顶圈梁→支护施工完毕。 2020版教材P288-294",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]